Tuesday, August 9, 2011

The Time Line This Far

5-12-11        Initial, pre-work photos taken.  All standard classroom furniture in place.

6-1-11        Furniture removed.  Nothing done toward abestos abatement.

6-17-11        No new work to date
6-21-11        No new work to date
6-23-11        No new work to date

7-2-11        Asbestos abatement begun.  Dropped ceiling panels removed.

7-7-11        Walls stripped.  Chalkboard removed.  Corner cabinet (where Kachelofen will be) still in place.

7-11-11        Richard Sink and family visit room to take measurements (according to Michael Walter)

7-14-11        Work on corner cabinet removal begun.  Hole in wall below.
7-20-11        Center of room partially screened off with uprights and plastic.
7-26-11        Plastic put up floor to ceiling in most of room sign saying "Danger Asbestos."  (As seen through peep hole).