5-12-11 Initial, pre-work photos taken. All standard classroom furniture in place.
6-1-11 Furniture removed. Nothing done toward abestos abatement.
6-17-11 No new work to date
6-21-11 No new work to date
6-23-11 No new work to date
7-2-11 Asbestos abatement begun. Dropped ceiling panels removed.
7-7-11 Walls stripped. Chalkboard removed. Corner cabinet (where Kachelofen will be) still in place.
7-11-11 Richard Sink and family visit room to take measurements (according to Michael Walter)
7-14-11 Work on corner cabinet removal begun. Hole in wall below.
7-20-11 Center of room partially screened off with uprights and plastic.
7-26-11 Plastic put up floor to ceiling in most of room sign saying "Danger Asbestos." (As seen through peep hole).